Borck Bridge Update May 2021
Thelin’s are making great progress with the bridge construction with the 4th pier being poured this week. 4 piers down and only 2 to go! Then we’ll really start seeing the bridge take shape once the beams start going on…
Thelin’s are making great progress with the bridge construction with the 4th pier being poured this week. 4 piers down and only 2 to go! Then we’ll really start seeing the bridge take shape once the beams start going on…
Structural Steel work on the commercial building in Central Park is now complete! The Coman Construction team have been busy this week installing pre-nail timber framing. Work on the roof structure will start in the coming weeks which will really…
By next week Thelin’s are hoping to have all in ground bridge foundations completed. Steel casings are already in for all piles and steel upstands in place for 2nd and 3rd piers. There is a heap of work ahead for…
Taylors Contracting and Not Just Concrete are currently constructing a large section of shared path along Borck Creek reserve for the Applebyfield Consortium. This concrete path is a continuation of the shared path which starts at Lower Queen Street and…
Construction of the Gibbons ”Berryfields Crossing” cinema and hospitality complex is progressing well. This multi-screen Silky Otter Cinema is planned to be opened by the end of this year. Exciting! Visit their websites: www.berryfieldscrossing.co.nz - www.silkyotter.co.nz
Check out the plan showing the extensive network of shared paths currently built and planned for construction in The Meadows, Borck Creek reserve and in the surrounding Richmond West area. The bold line shows the shared paths that have already…
Huge progress with earthworks in Stages 6, 7 & 8 over the past few months even in spite of all the rain we’ve had! Taylors Contracting have this week formed a large section of the new stormwater swale to where…
Stage 9B which includes the roads that complete the ring road around Central Park is progressing well. All services are now in and Ching’s have started prepping the road ready for kerbs to be poured in the New Year. Not…
Latest photos showing progress with the large number of new home builds underway in Stages 1, 2 & 4. It won't be long now until the first residents will be living in The Meadows
Today we released our next two stages in The Meadows. Our Stages 6 and 7 release comprises 39 sections - 29 standalone sections with a range of aspects and sizes as well as 10 townhouse sections which will overlook The…