Stage 9B Update

Stage 9B which includes the roads that complete the ring road around Central Park is progressing well. All services are now in and Ching’s have started prepping the road ready for kerbs to be poured in the New Year. Not Just Concrete have this week poured a large section of the shared path that will run on the ‘proposed school’ side of Central Park Lane.

The Building consent has finally been issued for the Central Park commercial building and Coman Construction are hoping to make a start on prepping the floor before Christmas.